On Shem Creek, the Shrimp Docks Top This Winter's Work List

October 22, 2026

When a creek needs dredging, has a damaged public dock and has a boardwalk that's wearing out, what does a town fix first? At an October 5 committee meeting, Mount Pleasant approved a dredging contract that names the commercial shrimp docks as the most pressing site. It also gave the boardwalk a year of design work before any boards change. The public floating dock stays closed, with no replacement announced.

The order matters to anyone who walks the creek, buys shrimp off it or launches a boat from Mill Street. Most of the visible creek will look the same through spring. The biggest changes this winter will happen below the waterline, at the docks where the boats tie up.

Mud Before Boards

At its October 5, 2026 Bids and Purchases meeting, the Town awarded a $1,179,220 dredging contract to Banks Construction Company, according to the committee minutes. The job covers three spots along the creek: the Town's shrimp docks, the floating day dock and the fixed lease docks. Crews can remove up to 6,520 cubic yards of material.

The work window opens December 1, 2026 and closes March 1, 2027. Everything has to be finished by April 1, 2027.

The minutes include three details that matter to anyone living near the creek:

  • The shrimp docks are the most urgent. Town staff called them the most pressing of the three sites. The floating docks and the fixed pier have not been dredged since 2014.
  • The mud leaves by water. Staff confirmed the sediment will be barged, not trucked through neighborhoods, to the South Carolina Ports dredge disposal site at the tip of Daniel Island. The Town has already secured that site.
  • Most of the money comes from outside the Town. The project is funded partly through a federal legislative earmark administered by the South Carolina Department of Parks, Recreation and Tourism. Staff said state appropriations of more than $1,000,000 made it possible.

Staff described the dredging mainly as an environmental project. Deeper water and less sediment on the creek bottom improve water exchange and water quality. A council member asked whether the repositioned Crab Bank has changed how sediment builds up in the creek. Staff said a dedicated study would be needed to answer that.

Why the Boats Go First

The shrimp docks top the list for a reason. Shem Creek is still a working waterfront, even with a much smaller fleet. In a 2025 report, The Post and Courier counted fewer than 10 shrimpers left on the creek. The same report named two Tarvin Seafood trawlers, the Miss Paula and the Carolina Breeze, and said Tarvin also buys shrimp from other boats and sells to restaurants, food trucks, caterers and retail markets. When a fleet is that small, every boat that can still reach its dock counts. The committee chair said much the same in the minutes, stressing the importance of keeping Shem Creek a working waterfront.

The schedule lines up with the shrimp season. The South Carolina Department of Natural Resources says the fall white-shrimp catch usually starts landing in August, peaks in September and October, and runs through December or sometimes into January. That is the general pattern, not a forecast for 2026. Even so, it means the dredging window opens on December 1, after the usual peak and while the season is winding down.

For residents, that leaves just under six weeks of normal dock activity before the dredging window opens. Tarvin Seafood sells retail at Wando Dock, 102 Haddrell Street. Its website lists hours of 10 a.m. to 3 p.m. Monday through Thursday, 10 a.m. to 5 p.m. Friday and Saturday, and 10 a.m. to 4 p.m. Sunday. The company also makes wholesale deliveries to restaurants every day. Orders are taken only by phone at 843-425-8695, not by email or online message. Retail hours can change with the season, so call before you drive over.

The Public Dock Is Already Out of Service

The Town closed the floating dock at Shem Creek Park on October 1, 2026 after it was damaged. According to the Town's notice, crews secured the structure and put a containment boom in the water to catch debris from a damaged flotation component. The Town expected to remove the dock by the end of the day Friday, October 2, depending on site conditions. The closure covers only the floating dock. The rest of Shem Creek Park, including the boardwalk, stayed open. The Town said it will determine the cause of the damage and decide next steps after the dock is removed and evaluated.

The floating day dock is also one of the three dredging sites. So the water at that spot is set to be dredged this winter, while the Town decides what happens to the dock itself.

The public boat ramp is a separate facility. Charleston County Parks runs the Shem Creek Boat Landing at 515 Mill Street, which has its own launch area and courtesy dock. Parking at the landing has been a long-running problem. In June, Live 5 News reported that the County's expansion plan would add 15 parking spaces. Drainage concerns and questions about tree removal sent the plan back for design review.

The Town has its own plan for the same problem. A new lot at 516 Coleman Boulevard would keep the existing number of parking spaces and add two EV charging spaces plus five spaces for boat trailers. Staff said the trailer spaces are meant to take pressure off the nearby boat landing. The recommended contract with Palmetto Tractor Services of South Carolina LLC totals $588,883.64, and construction would take 150 calendar days from the notice to proceed. On October 5, the committee sent the contract to full Town Council with no recommendation, because the full council had asked to weigh in. No start date has been set yet.

The Boardwalk Waits Its Turn

The boardwalk is the part of the creek residents use most, and it is last in line. At the same October 5 meeting, the committee approved a $378,978 design contract with GEL Engineering LLC. The firm will design replacements for Shem Creek Boardwalk 1, Boardwalk 2, and the wood-piling section of Boardwalk 3 west of the pedestrian bridge.

Here's what the minutes say about the boardwalk:

  1. Timing. Design and permitting are expected to take 12 months. The Public Services Director said the replacement will probably be built in phases over time.
  2. Why now. The boardwalks are inspected every few years, and recent inspections found the wear getting worse.
  3. Materials. The Town is looking at fiberglass pilings instead of wood and at composite decking. Composite decking already installed in areas that flood regularly has held up well. The goal is lower maintenance in a place where saltwater, wind and tides are hard on any structure.
  4. Height. No elevation changes are expected at this point. The engineered drawings will settle the details.

With a year of design and phased construction after that, the boardwalk you walk this winter is the same one you walked this summer. The decking won't change until the drawings and permits are done.

The Calendar From Here

All of this happens on top of an ordinary week on the creek. The newest stop is Shem Creek Outpost at 1411 Shrimp Boat Lane, which opened in July 2026 in a restored building that dates to 1945. Explore Charleston's October 8 roundup describes it as a waterfront shop and café selling bait and tackle, gifts, apparel, food, beer and ice cream, with Shem Creek merchandise alongside local brands and art. As of that roundup, breakfast, a craft sandwich café and dockside pickup were all listed as coming soon. Once dockside pickup starts, the Outpost will serve people arriving by boat as well as on foot.

Here are the dates in order, from this week through spring:

  1. Since October 1: The Shem Creek Park floating dock is closed. The boardwalk and the rest of the park are open.
  2. Late October through November: The tail end of the usual September–October white-shrimp peak, then the weeks after it. Wando Dock retail is open seven days a week, according to Tarvin's posted hours.
  3. To be scheduled: Full Town Council decides on the 516 Coleman Boulevard lot and its five boat-trailer spaces.
  4. December 1, 2026 to March 1, 2027: Dredging at the Town's shrimp docks, the floating day dock and the fixed lease docks, with sediment barged to Daniel Island.
  5. By April 1, 2027: Deadline for all dredging work.
  6. About October 2027: End of the estimated 12 months of boardwalk design and permitting, if the schedule holds. Phased replacement would follow.

The dredging window opens December 1 at three dock sites, and the boardwalk is the last part of the creek scheduled to change.

For waterfront homeowners and buyers watching Shem Creek, it helps to know which projects are funded, which are still being designed and which are waiting on a council vote. Livingston Group follows these timelines closely. If you'd like to talk through how the work on the creek affects your plans, schedule a complimentary strategy consultation.